The rule that drives the schedule
Reston Association's FAQ is direct: owners aren't permitted to undertake any construction related to a project, including tree removal, until they have the final written decision. That one sentence decides the shape of a Reston re-roof. Everything that depends on the approved product, from ordering to the start date, comes after the decision, and everything the application needs comes before it.
A practical order of operations
- Inspection. Find out whether you need a repair or a replacement, and what condition the deck, flashing, skylights and ventilation are in.
- Identify your review path. Cluster home, single-family home outside a cluster, condominium, Reston Town Center, or Lake Anne historic district: each has a different set of rules. Your covenants advisor can confirm.
- Read the standard. Find the roofing section of your cluster standard or the Design Guideline for your property type, plus anything on gutters, flues and skylights.
- Write the scope. Product line, color, skylight plan, gutter changes, decking approach and permit responsibility, all in writing.
- Approval. Either have your advisor verify and record a palette match, if your guideline allows it, or submit an application with photos and neighbor signatures.
- Read the decision. Note any conditions, and make sure the scope matches what was approved.
- Order and schedule. Confirm materials and set the start date only now.
- Build and complete. Install, walk the job, and file the decision letter with your scope.
Where time actually goes
We don't publish approval processing times, because they depend on the review level and RA's schedule. What we can say is where owners tend to lose time: hunting for a cluster standard after the roofer has already visited, collecting neighbor signatures when a neighbor is away, discovering the chosen color isn't on the palette, or having an application returned as incomplete. RA's own checklist notes that design review agendas are limited and recommends applying well before your planned installation date.
- Ask your covenants advisor which review level applies before you finalize a product.
- Collect signatures early. RA's FAQ says to show neighbors the full plans and materials; staff can advise if someone can't sign.
- Use RA's submittal checklist and sample roof application to avoid a returned package.
- Decide about skylights and gutter guards before applying, so you don't need a second round.
Who does what, and when
- You: confirm your review path with your covenants advisor, collect neighbor (and, in a cluster, officer) signatures, and submit the application.
- Us: inspect the roof, write the scope, and supply the product, color, material-type and photo details the application asks for.
- Reston Association: verify and record a palette match, or review the application at the level its guideline sets.
- Together: compare the decision with the scope, then set the order date and the start date.
Leaks and emergencies
A roof that is actively leaking can't always wait for a planned process. Temporary protection to stop water getting in is different from changing a roof's appearance. If storm damage forces the issue, document everything, protect the house, and contact your covenants advisor promptly about the permanent repair or replacement, especially if the existing shingle can't be matched.
The approval window
Approval isn't open-ended. RA's FAQ says approved work must begin within six months and be substantially complete within eighteen months, unless the decision stipulates otherwise. If you apply in winter for a spring roof, that's comfortably inside the window; if you apply and then postpone a year, check with your advisor before starting.
Weather
Roofing is outdoor work, and the schedule moves with rain, wind and temperature. Shingle manufacturers publish installation guidance for cold weather, and a roof that's torn off has to be dried in before rain. Build a little flexibility into your plans around the start date, and keep your roofer's contact handy for weather updates.
Permits in the schedule
Fairfax County lists replacement of roof shingles on homes as work that doesn't need a building permit, while roof repairs and some decking work do. If your scope needs a permit, add it to the schedule alongside the RA step. In the Lake Anne Village Center Historic Overlay District, the County's historic district FAQ says ARB approval applies to exterior alterations that require a building permit, so ask the County's heritage staff early.



Sources
Related pages
Can I order shingles before Reston Association approves them?▸
It's risky. If the color or product isn't approved, you may be stuck with materials you can't use. Order after the decision, or after your advisor has verified and recorded a palette match where that's allowed.
How long does Reston Association take to decide?▸
It depends on the review level and RA's schedule, so we don't quote processing times. Ask your covenants advisor, and apply well ahead of your planned start.
What if I approved a roof last year but never started?▸
RA's FAQ says work must begin within six months and be substantially complete within eighteen months unless the decision says otherwise. Check with your advisor before starting on an older approval.